Is the freight higher than the goods value? A hardcore review of winning a super duplex stainless steel fastener order in Casablanca, Morocco
Quick Overview
Purchased products: Super duplex stainless steel fasteners (UNS S32750 / EN 1.4410), including threaded rods, hex nuts, and flat washers
Product application: Pipeline connection
Key technical indicators: PREN > 40, EN 10204 3.1 MTC
Logistics solution: Urgent air freight to Casablanca Airport
Final trade term: CPT (Carriage Paid To)
|
DESIGNATION
|
SIZE
|
QIT
|
UM
|
|
Threaded Rod M24*500 - Super Duplex Stainless Steel UNS S32750 (EN 1.4410)
|
M24
|
110
|
PCS
|
|
Hex Nut M24 - Super Duplex Stainless Steel UNS S32750 (EN 1.4410) ISO 4032 - PREN 2 40
|
M24
|
300
|
PCS
|
|
Flat Washer M24-UNS S32750-ISO 7089 -PREN ≥40
|
M24
|
300
|
PCS
|
Part I. Urgent Inquiry: A Pipeline Connection Project in Morocco, North Africa

└Moroccan client inquiry for UNS S32750 threaded rods, hex nuts, and washers with short lead time.
|
No
|
Product Description
|
SIZE
|
Qty
|
Unit Price
(USD) |
Total Price
(USD) |
|
1
|
Threaded Rod M24x500mm-SuperDuplexStainlessSteelUNSS32750(EN1.4410) tensile strength ≥800
|
M24
|
110
|
19.87
|
2,185.70
|
|
2
|
Threaded Rod M24x500mm-SuperDuplexStainlessSteelUNSS32750(EN1.4410) tensile strength ≥760
|
M24
|
110
|
19.11
|
2,102.10
|
|
3
|
Hex Nut M24 - Super Duplex Stainless Steel UNS S32750 (EN 1.4410) ISO 4032 - PREN 2 40
|
M24
|
300
|
2.76
|
828.00
|
|
4
|
Flat Washer M24-UNS S32750-ISO 7089 -PREN ≥40
|
M24
|
300
|
1.02
|
306.00
|
|
Total
|
Ex-work
|
5,421.80
|

└We quickly reviewed the Moroccan inquiry and sent the UNS S32750 fastener quote the next day.
Part II. Crazy Freight Cost: Shocking Direct Air Freight Quotation

└After reviewing the quote, the Moroccan client requested air freight re-quote to shorten lead time.

└After checking, the air freight for these UNS S32750 fasteners to Morocco is USD 2,070.
Me: "By air: 2070 usd. really crazy" (Air freight costs 2070 USD, really crazy)
Client: "hahaha it's not me the client" (Hahaha, it's not me, the client, paying)
Part III. Hardcore Technical Aspect: UNS S32750 and MTC Verification of PREN > 40

└Moroccan client requires super duplex stainless steel, PREN>40, and MTC certificate after receiving PO.

└We confirmed the details by email and sent the PI and MTC raw material report.
Part IV. Delivery Schedule Game and Raw Material Price Increase Crisis

└After receiving documents, Moroccan client requested production under 35 days, finally agreed.

└A week later, no deposit received; raw material price rose 6%, client insisted on the original quote.

└Stainless and duplex steel prices surged; fast payment keeps the old price, but the client didn't reply.

└Moroccan client urged us to send the MTC report and requested “Material UNS S32750 with PREN > 40”.

└Moroccan client requested a super duplex MTC; we sent the certificate from the previous shipment.
Part V. Ultimate Showdown of Trade Terms: How to Choose Between CIF, CFR, and CPT in Air Freight Scenarios?

└Moroccan client requested changing the UNS S32750 fastener order from DDU to DDP or DAP.

└We negotiated customs clearance for UNS S32750 fasteners; Moroccan client wanted CFR, not CIF.

└We confirmed: air freight to the airport with Moroccan client clearing customs and picking up is CPT.
Applicability to air freight: Also mainly aimed at sea freight.
Applicability to air freight: The most standard and best-matching term for air freight.

└Moroccan client negotiated air freight and goods price for UNS S32750 fasteners; finally agreed.

└To speed up payment, the Moroccan client added the boss and finance manager to the group chat.
Part VI. Self-Verification of Qualifications: The Company Name Change Incident and Video Factory Inspection

└Moroccan client transferred the UNS S32750 fastener deposit and sent us the bank slip.

└Moroccan client found a company name mismatch between certificate and PI; misunderstanding resolved.

└We provided business license, bank slip, and visitor photos to finally resolve the Moroccan client's doubts.
Part VII. Production Follow-up and Smooth Pickup

└Moroccan client sent payment; after receiving the UNS S32750 fastener deposit, we arranged production.

└We updated milestones: semi-finished nuts/washers, raw materials arrival, and threaded rod production.

└After production, we inspected the appearance and material of the UNS S32750 fasteners.

└Moroccan client was satisfied after receiving the test report and paid the UNS S32750 fastener balance.

└After balance payment, I sent the Moroccan client packing photos and shipping mark images of fasteners.

└Moroccan client received the UNS S32750 fasteners, was satisfied, and willing to continue cooperation.
FAQ
Do you accept custom labeling and other customized services?
How small can a first order be if I only need a trial batch?
What is the lead time - do you ship from stock or produce to order?
How can I verify that this Moroccan fastener order is real?